5.9 Estimate Activity Durations

5.9 Estimate Activity Durations
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

  • Determine how much time each defined activity needs to be completed under expected conditions.
  • Used during planning after activities and resources are identified, and revisited whenever scope, resources, or risks change.
  • Feeds the schedule model, critical path analysis, milestones, and time-related risk and cost decisions.
  • Improves predictability by making assumptions, constraints, and uncertainty visible.

Mini Flow (How It’s Done)

  • Review inputs: activity list and attributes, resource needs and assignments, calendars, scope details, assumptions, risks, and historical data.
  • Engage estimators: involve the people who will do the work, relevant experts, and suppliers to validate approach and rates.
  • Select techniques: use analogous (by comparison), parametric (rates × quantities), three‑point (optimistic, most likely, pessimistic), bottom‑up (roll up from detailed tasks), and reserve analysis as appropriate.
  • Consider drivers: resource availability and skill, productivity, learning curve, work windows, dependencies, constraints, tools, quality standards, and known risks.
  • Calculate durations: apply chosen methods, convert to working time using calendars, and where using three‑point, compute an expected value and a range.
  • Assess uncertainty: add time contingency for known risks in activities or as task buffers; keep any management reserve separate from the baseline.
  • Document the basis: sources, assumptions, methods, ranges, confidence level, and key constraints for each estimate.
  • Update records: revise activity attributes, risk and assumptions logs, lessons learned, and schedule data; share for review and agreement.

Quality & Acceptance Checklist

  • Each activity has a duration in working time units and aligns with the defined scope.
  • Assumptions and constraints affecting time are clearly documented.
  • Estimation method used and data sources are recorded and traceable.
  • Resource calendars, availability, and skill levels are reflected in the numbers.
  • Uncertainty is expressed as ranges and/or confidence levels; risk‑based contingency is visible, not hidden.
  • Dependencies, leads, and lags are explicit and justifiable.
  • Estimates are reviewed by the people doing the work and relevant experts.
  • Units are consistent across all activities and milestones.
  • The basis of estimates is stored for future updates and audits.
  • Updates are triggered when scope, resources, or risk responses change.

Common Mistakes & Exam Traps

  • Confusing effort (person‑hours) with duration (elapsed time), especially when resource availability is part‑time.
  • Ignoring calendars and resource constraints, leading to calendar‑day estimates instead of working‑day estimates.
  • Using analogous estimates when projects are not truly comparable, or parametric rates without validated productivity data.
  • Providing single‑point numbers with no ranges or risk consideration, or hiding padding instead of using transparent contingency.
  • Estimating without involving those who will perform the work, increasing optimism bias.
  • Failing to update durations after approved scope changes or risk responses like crashing or fast tracking.
  • Assuming adding people will always shorten duration, ignoring coordination overhead and task type.
  • Misusing leads and lags to mask schedule problems rather than modeling real dependencies.

PMP Example Question

A specialist needed for a critical activity will be available only 50% next month. The team previously estimated the activity as 40 hours of effort over one week. What should the project manager do to improve the duration estimate?

  1. Add a management reserve to the schedule to cover the risk.
  2. Apply the resource calendar and re‑estimate duration based on 50% availability.
  3. Add more people to the activity to keep the one‑week duration.
  4. Ask the sponsor to confirm the one‑week deadline.

Correct Answer: B — Apply the resource calendar and re‑estimate duration based on 50% availability.

Explanation: Duration depends on resource availability. With half‑time availability, 40 hours of effort will span about two weeks of elapsed time, assuming no other constraints.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.



Launch your career!

HK School of Management delivers top-tier training in Project Management, Job Search Strategies, and Career Growth. For the price of a lunch, you’ll gain expert insights into landing your dream PM role, mastering interviews, and negotiating like a pro. With a 30-day money-back guarantee, there’s zero risk—just a clear path to success!

Learn More