Variance Analysis

A method used to identify why results differ from the baseline and to measure how large those differences are.

Key Points

  • Compares actual results to baseline plans for cost, schedule, and other performance areas.
  • Quantifies the size of the deviation and investigates root causes.
  • Supports corrective and preventive actions and informs forecasts (for example, EAC in EVM).
  • Performed during monitoring and controlling, often alongside trend and earned value analysis.

Example

At the end of month 3, the project planned value is USD 300,000, earned value is USD 250,000, and actual cost is USD 280,000. Variance analysis shows SV = -50,000 and CV = -30,000. The team traces the cause to a vendor delay and overtime costs, then updates the schedule and cost forecasts and implements corrective actions.

PMP Example Question

During Control Costs, the project manager sees that actual costs are higher than planned. Which technique should be used to determine why the deviation occurred and how large it is compared to the baseline?

  1. Trend analysis
  2. Variance analysis
  3. What-if scenario analysis
  4. Reserve analysis

Correct Answer: B — analyzing differences from the plan and their causes

Explanation: Variance analysis compares actuals to the baseline to quantify the gap and identify root causes, enabling targeted corrective action.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included