Update

A change made to a deliverable, a component of the project management plan, or a project document that is not subject to formal change control.

Key Points

  • No formal change request or board approval is required because the item is not baselined or formally controlled.
  • Should be recorded through versioning or a revision history to maintain transparency and traceability.
  • Commonly applied to project documents such as the issue log, risk register entries, stakeholder register, or team directory.
  • Must not change baselines or other controlled artifacts; those require formal change control.

Example

After a stakeholder meeting, the project manager adds a new stakeholder and updates contact details in the stakeholder register. The revision is dated and noted, but no change request is submitted because the register is not under formal change control.

PMP Example Question

During execution, a tester adds a newly discovered defect to the issue log and updates its priority without submitting a change request. What is this action called?

  1. Update
  2. Change request
  3. Corrective action
  4. Preventive action

Correct Answer: A — Update

Explanation: The issue log is typically not under formal change control, so revising it is an update, not a formal change request or corrective/preventive action.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course