Trigger Condition

A specific sign or circumstance that warns a risk event is likely to happen soon.

Key Points

  • Serves as an early warning indicator that a known risk may materialize.
  • Defined and recorded in the risk register during risk planning.
  • Monitored throughout the project to decide when to launch risk responses.
  • Often tied to clear thresholds or metrics (e.g., dates missed, counts exceeded).

Example

In a software project, the team sets a trigger condition: "Open critical defects exceed 30 for three days in a row." When this occurs, the project manager initiates the contingency plan to add test resources and re-sequence tasks to reduce schedule risk.

PMP Example Question

Which term refers to a predefined sign, such as "the supplier misses two consecutive delivery milestones," that prompts the team to activate a risk response plan?

  1. Trigger condition
  2. Risk owner
  3. Residual risk
  4. Risk tolerance

Correct Answer: A — Trigger condition

Explanation: A trigger condition is a monitored indicator or circumstance that signals a risk is imminent and that the planned response should be executed.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Run the drill before the incident runs you

Design, run and prove OT drills and tabletop exercises before an incident tests your team. OT Incident Drills and Exercises includes 24 lessons and practical exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course