Total Float

The maximum time an activity can start later or take longer, relative to its early start, without pushing the overall project finish date or breaking any imposed schedule constraints.

Key Points

  • Indicates schedule flexibility that does not change the project's completion date or violate constraints.
  • Calculated as LS - ES or LF - EF in the network schedule.
  • Activities on the critical path typically have zero total float; negative float signals the plan cannot meet a required date.
  • Float on a path is shared by its activities; using it on one activity reduces what is available to others on the same path.

Example

Activity B has ES = day 5 and EF = day 9. Its LS = day 7 and LF = day 11. Total float = LS - ES = 2 days (or LF - EF = 2 days). B can start up to two days late or run two days longer without moving the project's finish or breaking a constraint.

PMP Example Question

A task shows a total float of 3 days. What does this allow the project manager to do?

  1. Delay the task by up to 3 days without affecting the project finish date.
  2. Delay the task by up to 3 days without affecting any successor's early start.
  3. Add 3 days of scope to the task without any impact.
  4. Crash the task by 3 days with no additional cost.

Correct Answer: A — Delay the task without moving the project completion date

Explanation: Total float is the time an activity can slip or extend relative to its early start without changing the project finish date or violating schedule constraints. Option B describes free float.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Launch your career!

HK School of Management and Technology offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More