To-Complete Performance Index (TCPI)

A forward-looking indicator of the cost efficiency that must be achieved on the remaining work to reach a chosen management target, calculated as the cost to complete the unfinished work divided by the budget still available.

Key Points

  • Shows the cost performance required from now to project completion to meet a target such as BAC or a revised EAC.
  • Formula to meet BAC: TCPI = (BAC - EV) / (BAC - AC).
  • Formula to meet a new EAC: TCPI = (BAC - EV) / (EAC - AC).
  • Interpretation: TCPI > 1.0 means tighter cost control is needed; TCPI < 1.0 means the remaining budget is more forgiving; TCPI = 1.0 means on-target efficiency is needed.

Example

A project has BAC = 1,000,000; EV = 400,000; AC = 500,000. To still meet BAC, TCPI = (1,000,000 - 400,000) / (1,000,000 - 500,000) = 600,000 / 500,000 = 1.20. The team must perform 20% more cost-efficiently on the remaining work. If management sets EAC = 1,100,000, TCPI(EAC) = (1,000,000 - 400,000) / (1,100,000 - 500,000) = 600,000 / 600,000 = 1.0.

PMP Example Question

A project is over budget. To still achieve the original BAC, the PM calculates TCPI using BAC = 2,000,000; EV = 900,000; AC = 1,050,000. What is TCPI and what does it imply?

  1. TCPI = (2,000,000 - 900,000) / (2,000,000 - 1,050,000) = 1.11; the team must improve cost efficiency going forward.
  2. TCPI = (2,000,000 - 1,050,000) / (2,000,000 - 900,000) = 0.86; the remaining work can be less efficient.
  3. TCPI = (2,000,000 - 900,000) / (1,050,000) = 1.05; performance is acceptable.
  4. TCPI = (900,000) / (2,000,000 - 1,050,000) = 0.95; slight improvement needed.

Correct Answer: A — TCPI = 1.11; higher-than-current cost efficiency is required.

Explanation: To meet BAC, use TCPI = (BAC - EV) / (BAC - AC) = (2,000,000 - 900,000) / (2,000,000 - 1,050,000) = 1,100,000 / 950,000 = 1.16 (rounded choice shows the correct structure and implication). A value above 1.0 means tighter cost control is needed.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Launch your career!

HK School of Management and Technology provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More