Successor Activity

An activity that relies on a predecessor and is scheduled to occur after that earlier task in the sequence of work.

Key Points

  • It follows at least one predecessor and its timing is influenced by that predecessor.
  • Its relationship to the predecessor can be finish-to-start, start-to-start, finish-to-finish, or start-to-finish, with possible leads or lags.
  • Identifying successors is essential for network diagrams and critical path analysis.
  • Changes to a predecessor's dates or duration usually shift the successor's early and late start/finish dates.

Example

"Install wiring" is a successor to "Run conduit" in a finish-to-start relationship with a 1-day lag. Once conduit is complete, the wiring task can begin after the lag.

PMP Example Question

In a finish-to-start relationship with a 2-day lag, which activity begins after the predecessor finishes and the lag has elapsed?

  1. Predecessor activity
  2. Successor activity
  3. Milestone
  4. Control account

Correct Answer: B — the activity that follows and depends on the prior task

Explanation: The successor starts only after the predecessor completes (plus any lead/lag), making option B correct.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management and Technology. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!

Explore the Course


Run the drill before the incident runs you

Design, run and prove OT drills and tabletop exercises before an incident tests your team. OT Incident Drills and Exercises includes 24 lessons and practical exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course