Start-to-Start (SS)

A dependency where the successor activity cannot begin until the predecessor activity has begun.

Key Points

  • The successor may not start until the predecessor has at least started.
  • Once the predecessor starts, both activities can proceed in parallel.
  • You can add lead or lag to shift the successor's start relative to the predecessor's start.
  • Controls start times only; it does not determine when either activity finishes.

Example

In a software project, begin integration testing 2 days after development starts. This is an SS relationship with a 2-day lag.

PMP Example Question

Activity B can start only after Activity A has started, and both may run concurrently. What dependency is this?

  1. Finish-to-Start (FS)
  2. Start-to-Start (SS)
  3. Finish-to-Finish (FF)
  4. Start-to-Finish (SF)

Correct Answer: B — Start-to-start relationship (SS)

Explanation: SS ties the start of the successor to the start of the predecessor; the successor cannot begin until the predecessor has begun.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management and Technology. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!

Explore the Course


Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More