Start-to-Finish (SF)

A dependency where an earlier activity is not allowed to complete until the later activity has begun.

Key Points

  • The predecessor cannot finish until the successor has started.
  • This relationship is uncommon and often used for shift handoffs or custodial control.
  • You can apply lag so the predecessor finishes some time after the successor starts.
  • It restricts only the predecessor's finish; it does not set when either task must start or when the successor must finish.

Example

The night support team (predecessor) cannot end their shift until the day support team (successor) starts work. The start of the day shift authorizes the night shift to finish.

PMP Example Question

Which dependency best models a scenario where an outgoing operations team cannot close their activities until the incoming team begins their shift?

  1. Finish-to-Start (FS)
  2. Start-to-Start (SS)
  3. Start-to-Finish (SF)
  4. Finish-to-Finish (FF)

Correct Answer: C — Start-to-Finish (SF) relationship

Explanation: In an SF dependency, the predecessor's finish is contingent on the successor's start, which matches a shift handover scenario.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.

Explore the Course


Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More