Simulation

A quantitative method that imitates project outcomes under multiple uncertainties to assess how those combined variations could influence objectives.

Key Points

  • Runs many iterations using random inputs to reflect uncertainty and produce a range of possible results.
  • Often applied to cost and schedule to estimate the likelihood of meeting targets and required contingency.
  • Needs input ranges, probability distributions, and any correlations among variables to be credible.
  • Outputs include probabilities (e.g., P50, P80), outcome ranges, and sensitivity to key drivers.

Example

A project team assigns three-point estimates and distributions to activity durations and costs, then runs a Monte Carlo simulation with 10,000 iterations. The results show a 72% chance of finishing by November 30, a P80 cost of $1.95M, and a tornado chart revealing two design tasks as the main drivers of schedule risk.

PMP Example Question

A project manager wants to know the probability of finishing within 30 weeks and under $2M, given uncertain activity durations and material prices. Which technique should be used?

  1. Sensitivity analysis
  2. Simulation (Monte Carlo)
  3. Three-point estimating
  4. Trend analysis

Correct Answer: B — Simulation

Explanation: Simulation models the combined effect of multiple uncertainties to produce probability-based outcomes for time and cost objectives.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Launch your career!

HK School of Management and Technology offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More