Schedule Variance (SV)

An indicator of schedule performance calculated as earned value (EV) minus planned value (PV).

Key Points

  • Formula: SV = EV - PV; positive SV means ahead of schedule, negative SV means behind, zero means on plan.
  • SV uses the same units as EV and PV (e.g., dollars, labor hours), not time units.
  • Use with SPI (EV/PV) and trend analysis for better context; SV alone does not reveal critical path status.
  • At project completion SV = 0 because EV equals PV; early fluctuations can reflect baseline distribution.

Example

At month 4, PV = $200,000 and EV = $180,000. SV = 180,000 - 200,000 = -$20,000, indicating the project is behind schedule by $20,000 worth of planned work.

PMP Example Question

At the end of month 3, EV = $750,000, PV = $600,000, and AC = $800,000. What does the schedule status indicate based on SV?

  1. SV = -$150,000; the project is behind schedule.
  2. SV = +$150,000; the project is ahead of schedule.
  3. SV = -$200,000; the project has a cost overrun.
  4. Schedule status cannot be determined without the BAC.

Correct Answer: B — SV = EV - PV = +$150,000; ahead of schedule

Explanation: SV compares earned value to planned value. Since EV exceeds PV by $150,000, the project is ahead of schedule.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Lead with clarity, influence, and outcomes.

HK School of Management and Technology offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More