Schedule Performance Index (SPI)

An indicator of schedule efficiency calculated by dividing earned value (EV) by planned value (PV).

Key Points

  • Formula: SPI = EV / PV; it compares authorized work accomplished to the work that was planned by this point.
  • Interpretation: SPI > 1.0 means ahead of schedule, SPI = 1.0 means on schedule, SPI < 1.0 means behind schedule.
  • Use only when PV > 0 and when EV and PV are measured against the same baseline; track SPI trends to monitor schedule health and forecast performance.
  • SPI shows relative schedule progress, not calendar time impact; combine with critical path analysis and CPI for a fuller picture.

Example

By the end of month 3, PV is 150 units of work and EV is 120 units. SPI = 120 / 150 = 0.80. The team is progressing at 80 percent of the planned rate, indicating the project is behind schedule.

PMP Example Question

A project reports EV = 275 and PV = 250 near the end of a phase. What is the SPI and how should the project manager interpret it?

  1. 0.91; the project is behind schedule
  2. 1.10; the project is ahead of schedule
  3. 1.00; the project is on schedule
  4. 1.10; the project is over budget

Correct Answer: B — SPI of 1.10; the project is ahead of schedule

Explanation: SPI = EV / PV = 275 / 250 = 1.10. An SPI greater than 1 indicates the project is ahead of schedule; cost status is not assessed by SPI.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More