Schedule Network Analysis

A method that examines the schedule network to calculate the earliest and latest possible start and finish times for the remaining parts of project activities.

Key Points

  • Uses the schedule network diagram with activity durations and dependencies as inputs.
  • Applies forward and backward passes to compute ES, EF, LS, LF, and float.
  • Reveals the critical path and where schedule flexibility exists.
  • Repeated as the schedule is updated at the data date to reflect progress and changes.

Example

In a construction project, the scheduler updates actuals and then runs schedule network analysis. The forward and backward passes show that inspections are on the critical path with zero float, while interior painting has 2 days of total float. The project manager reallocates crew members to critical activities to protect the completion date.

PMP Example Question

Which technique examines the schedule network to determine early and late start/finish dates and identify schedule flexibility?

  1. Resource smoothing
  2. Schedule network analysis
  3. Rolling wave planning
  4. Monte Carlo simulation

Correct Answer: B — Schedule network analysis

Explanation: Schedule network analysis uses forward and backward passes on the network to calculate ES, EF, LS, LF, and float, highlighting the critical path. The other options do not compute these dates.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Lead with clarity, influence, and outcomes.

HK School of Management and Technology offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More