Schedule Compression

A method to shorten the overall project timeline without changing the agreed scope.

Key Points

  • Achieved mainly through fast-tracking (overlapping work) and crashing (adding resources to critical tasks).
  • Focuses on activities on the critical path; compressing non-critical work may not affect the finish date.
  • Often increases cost and/or risk, so trade-offs must be analyzed before applying.
  • Requires re-analysis of the schedule and stakeholder agreement on impacts and assumptions.

Example

A construction project is slipping. The PM overlaps foundation curing with early framing (fast-tracking) and brings in an extra crew for framing (crashing) to pull the completion date back without changing deliverables.

PMP Example Question

A project must meet a deadline without removing any deliverables. What should the project manager do?

  1. Apply schedule compression by fast-tracking critical path activities.
  2. Reduce lower-priority requirements to save time.
  3. Level resources across all tasks to balance workload.
  4. Add extra features to increase stakeholder satisfaction.

Correct Answer: A — Schedule compression

Explanation: Schedule compression shortens the timeline without changing scope. Scope reduction changes scope, resource leveling often lengthens duration, and gold plating adds unnecessary work.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More