Schedule Baseline

The authorized baseline of the project's time model that may be updated only through the formal change control process and serves as the reference point for comparing planned versus actual results.

Key Points

  • Represents the frozen plan for activity dates, milestones, and dependencies at a given point in time.
  • Changes require an approved change request through the integrated change control process.
  • Used to measure schedule variance and performance trends against what was originally planned.
  • May be rebaselined only when significant, approved changes make the original baseline no longer realistic.

Example

A construction project sets its schedule baseline at the end of planning, locking in key milestone dates and activity sequences. When unexpected soil issues delay foundation work, the team submits a change request. Only after formal approval is the baseline updated; until then, progress is reported and variances are calculated against the original baseline dates.

PMP Example Question

Midway through a project, the team discovers a two-week delay on the critical path. To report variance accurately, what should the project manager compare the current forecasted finish dates against?

  1. The latest resource calendar
  2. The product backlog
  3. The schedule baseline
  4. The risk register

Correct Answer: C — The schedule baseline

Explanation: Variance is measured by comparing actuals and forecasts to the approved schedule baseline, which is the official reference for performance measurement.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More