Schedule

A time-phased plan that shows the intended start and finish dates for project activities, milestones, and deliverables; it is generated from the schedule model and used to direct, communicate, and control work.

Key Points

  • The schedule is the dated result; the schedule model is the data, logic, calendars, and rules used to compute it.
  • Can be presented as milestone, summary/master, or detailed schedules in formats such as Gantt charts, network diagrams, or calendars.
  • Supports control by exposing dependencies, critical path, float, constraints, and resource needs for baseline and forecast views.
  • See project schedule and schedule model.

Example

On a software project, the PM builds the schedule in a tool by sequencing design, development, testing, and deployment, assigns calendars, and baselines the dates. Each week the team updates progress; the PM reviews the critical path and float to forecast the release date and plans corrective actions if slippage appears.

PMP Example Question

Which statement best describes the project schedule?

  1. A repository of activities, relationships, calendars, and rules used to calculate dates.
  2. A time-phased plan with planned start and finish dates for activities and milestones used to guide and monitor execution.
  3. A list of resources and costs assigned to each work package.
  4. A prioritized backlog that orders features by business value.

Correct Answer: B — A dated plan of activities and milestones

Explanation: The project schedule is the dated plan used to manage work. Option A describes the schedule model; C is a cost/resource list; D is an agile backlog.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More