Risk Audit

An audit that evaluates how well the project's risk management approach and actions are working.

Key Points

  • Assesses the effectiveness and efficiency of risk identification, analysis, response planning, and monitoring.
  • Reviews the risk register, owners, response status, triggers, and use of reserves to find gaps and improvements.
  • Leads to recommendations, corrective actions, and updates to the risk management plan and lessons learned.
  • Can be performed by the project team, PMO, or independent reviewers at planned intervals or major milestones.

Example

Midway through a construction project, the PM organizes a risk audit with the PMO. They discover that response plans for supplier delays lack clear triggers and owners. The team assigns owners, defines early warning indicators, updates the risk register, and adjusts contingency reserves.

PMP Example Question

Midway through a project, the PM wants to determine whether current risk responses are working and improve the overall risk process. What should the PM conduct?

  1. Risk audit
  2. Risk reassessment
  3. Variance analysis
  4. Root cause analysis

Correct Answer: A — Risk audit

Explanation: A risk audit specifically evaluates the effectiveness of the risk management process and responses. Reassessment updates risks, variance analysis compares performance to plan, and root cause analysis investigates underlying causes of issues.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management and Technology. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!

Explore the Course


Run the drill before the incident runs you

Design, run and prove OT drills and tabletop exercises before an incident tests your team. OT Incident Drills and Exercises includes 24 lessons and practical exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course