Responsibility

A delegated task or obligation defined in the project management plan that creates a duty for the assigned resource to complete the work and meet the assignment's requirements.

Key Points

  • It is a duty created by assigning work to a specific resource.
  • Responsibilities can be delegated, but the assignee must perform the required work.
  • They are typically documented in tools like a RACI chart or responsibility assignment matrix.
  • Responsibility focuses on doing the work, distinct from authority (power) and accountability (answerability).

Example

The project plan assigns the QA lead responsibility for preparing and executing the system test plan for Release 1. This means the QA lead must produce the test cases, run them on schedule, log defects, and meet the defined quality criteria.

PMP Example Question

Which statement best describes a responsibility in a project?

  1. The sponsor's ultimate answerability for project outcomes.
  2. A delegated duty recorded in the plan that requires the assignee to carry out specified work.
  3. The formal power to approve scope changes and allocate budget.
  4. The method used to categorize stakeholders by power and interest.

Correct Answer: B — A delegated duty requiring the assigned resource to perform the work

Explanation: Responsibility is a duty created by assignment of work in the plan; it obligates the assignee to complete the task according to requirements.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More