Resource Smoothing

A resource optimization method that adjusts noncritical activities within their available free and total float to reduce resource peaks, without changing the critical path or project completion date.

Key Points

  • Uses only free and total float; the critical path and finish date remain unchanged.
  • Shifts start or finish dates of noncritical work to even out resource usage.
  • Targets peak resource demand to keep it within defined limits or availability.
  • Unlike resource leveling, it does not extend the schedule or alter the critical path.

Example

A designer is overallocated on two parallel tasks that are not on the critical path. Each task has 3 days of float. The PM moves one task 2 days later, staying within its float. The designer's workload is balanced, and the project finish date and critical path do not change.

PMP Example Question

A project manager wants to remove resource overallocations but must keep the project finish date and critical path unchanged. What technique should be used?

  1. Delay noncritical activities within available float to reduce resource peaks
  2. Extend the project duration to resolve resource conflicts
  3. Crash critical path activities to free up resources
  4. Fast track by overlapping critical path activities

Correct Answer: A — Resource smoothing

Explanation: Resource smoothing uses free and total float to fix overallocations without affecting the critical path or finish date; leveling can change both.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More