Quality Control Measurements

Recorded outputs from performing Control Quality that show how products or processes actually performed against defined quality metrics.

Key Points

  • They are the output of the Control Quality process and capture actual inspection and test results.
  • Values may be numeric (e.g., defect counts, dimensions) or categorical (e.g., pass/fail) and are traceable to specific quality metrics.
  • They feed Manage Quality and analysis tools (e.g., trend charts) to drive process improvements and corrective actions.
  • They are stored as project records to support decisions, change requests, and lessons learned.

Example

On a software project, the team runs system tests and logs 38 defects with severity levels, pass/fail rates for 250 test cases, and response time measurements versus targets. These logged figures are the quality control measurements used to assess compliance and to plan fixes.

PMP Example Question

Which artifact should the project manager review to see the actual results from inspections and tests performed during Control Quality?

  1. Quality control measurements
  2. Quality metrics
  3. Quality management plan
  4. Verified deliverables

Correct Answer: A — Quality control measurements

Explanation: Quality control measurements contain the documented results from Control Quality. Metrics define targets, the plan explains the approach, and verified deliverables are items that passed inspection.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Launch your career!

HK School of Management and Technology provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More