Project Schedule Network Diagram

A diagram that visually shows the dependencies and sequencing among activities in the project schedule.

Key Points

  • Displays activity nodes and the logical links that define order and dependency (FS, SS, FF, SF).
  • Used to identify the critical path, total/float values, and potential bottlenecks.
  • Supports schedule development, what-if analysis, and compression techniques like fast tracking and crashing.
  • Often created with the precedence diagramming method; leads and lags can be shown on relationships.

Example

In a software project, "Develop Feature A" must finish before "System Test" can start (finish-to-start). "Prepare Test Data" can begin once "Design Complete" starts (start-to-start) with a 2-day lag. The network diagram maps these links so the team can find the critical path and schedule buffers.

PMP Example Question

Which artifact best illustrates how activities depend on one another in the project schedule?

  1. Work Breakdown Structure (WBS)
  2. Project Schedule Network Diagram
  3. RACI Matrix
  4. Milestone List

Correct Answer: B — Project Schedule Network Diagram

Explanation: The network diagram visually presents the logical relationships (dependencies and sequence) among schedule activities.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More