Procurement Audits

A systematic examination of contracts and the end-to-end procurement process to verify they are complete, accurate, and producing the intended outcomes, while capturing lessons to improve future procurements.

Key Points

  • Conducted during or after Control Procurements to identify what worked, what did not, and how to improve.
  • Reviews contract files, SOWs, change orders, approvals, invoices, and performance records for compliance and traceability.
  • Often led by an independent auditor or PMO to ensure objectivity; results feed lessons learned and process improvements.
  • Findings can trigger corrective actions, updates to templates and checklists, and help detect risks, noncompliance, or fraud.

Example

Midway through a project with several vendors, the PMO performs a procurement audit and discovers missing approvals on change orders and inconsistent acceptance criteria. The team standardizes forms, updates the contract change process, and retrains staff, reducing payment disputes and improving vendor performance for the remainder of the project.

PMP Example Question

Which activity systematically examines procurement documents and practices to confirm they are complete, correct, and effective, with the intent to improve future procurements?

  1. Procurement audits
  2. Inspection of deliverables
  3. Performance reviews
  4. Contract change control

Correct Answer: A — Procurement audits

Explanation: Procurement audits specifically review contracts and procurement processes for completeness, accuracy, and overall effectiveness, and capture lessons learned. The other options focus on product quality, team performance, or managing changes, not the end-to-end procurement process.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Launch your career!

HK School of Management and Technology offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More