predictive approach

A development method where scope, schedule, and cost are defined early in the life cycle and managed against set baselines.

Key Points

  • Plans and baselines for scope, schedule, and budget are created upfront and guide delivery.
  • Best for stable, well-understood requirements and low technical uncertainty.
  • Changes are controlled through formal change control and impact analysis.
  • Progress is tracked against the plan using milestones, phase gates, and variance analyses.

Example

A government office build-out with fixed requirements and strict codes uses a predictive approach: the team completes detailed design, creates a WBS and schedule, sets scope/schedule/cost baselines, and manages any requested changes through a formal change control board.

PMP Example Question

A project has stable requirements, a fixed budget and deadline, and significant compliance documentation. Which development approach is most appropriate?

  1. Predictive approach
  2. Iterative approach
  3. Incremental approach
  4. Hybrid approach

Correct Answer: A — Predictive approach

Explanation: When scope, time, and cost are determined early and must be tightly controlled, a predictive approach with formal baselines and change control is most suitable.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More