Predecessor Activity

A task that must occur before another, dependent task in the project schedule.

Key Points

  • Defines the logical order of tasks and establishes dependencies between activities.
  • Can be linked with different relationship types (FS, SS, FF, SF) along with leads or lags.
  • An activity may have multiple predecessors, a single predecessor, or none at project start.
  • Predecessor and successor relationships influence the critical path and schedule flexibility.

Example

In a building project, "Complete foundation" must finish before "Start framing" can begin. "Complete foundation" is the predecessor activity; "Start framing" is its successor.

PMP Example Question

Which statement best describes a predecessor activity?

  1. A task that starts only after its successor finishes.
  2. A task that must occur before a dependent task in the schedule.
  3. A task that is not linked to any other activity.
  4. A task that represents the longest path through the schedule network.

Correct Answer: B — a task that must occur before a dependent task

Explanation: A predecessor activity is one that logically comes before another activity that depends on it.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More