Predecessor Activity

A task that must occur before another, dependent task in the project schedule.

Key Points

  • Defines the logical order of tasks and establishes dependencies between activities.
  • Can be linked with different relationship types (FS, SS, FF, SF) along with leads or lags.
  • An activity may have multiple predecessors, a single predecessor, or none at project start.
  • Predecessor and successor relationships influence the critical path and schedule flexibility.

Example

In a building project, "Complete foundation" must finish before "Start framing" can begin. "Complete foundation" is the predecessor activity; "Start framing" is its successor.

PMP Example Question

Which statement best describes a predecessor activity?

  1. A task that starts only after its successor finishes.
  2. A task that must occur before a dependent task in the schedule.
  3. A task that is not linked to any other activity.
  4. A task that represents the longest path through the schedule network.

Correct Answer: B — a task that must occur before a dependent task

Explanation: A predecessor activity is one that logically comes before another activity that depends on it.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More