Parametric Estimating

An estimating approach that applies mathematical models or unit rates to historical data and specific project parameters to forecast total cost or duration.

Key Points

  • Uses measurable drivers (e.g., cost per unit, hours per feature) multiplied by quantities to produce estimates.
  • Depends on reliable historical data and clearly defined parameters for accuracy.
  • Models can be simple linear rates or more complex algorithms with multiple variables.
  • Often more accurate than analogous estimating when the scope and parameters are well understood.

Example

A construction team estimates flooring installation using a rate of $12 per square foot based on past projects. For 8,000 square feet, the cost estimate is 8,000 x $12 = $96,000. They adjust the rate by +10% for a premium material, resulting in $105,600.

PMP Example Question

Which estimating technique derives total effort by multiplying historical productivity rates by the number of units to be produced?

  1. Analogous estimating
  2. Parametric estimating
  3. Bottom-up estimating
  4. Three-point estimating

Correct Answer: B — Parametric estimating

Explanation: Parametric estimating uses historical rates or algorithms (e.g., cost or hours per unit) applied to known quantities to calculate an overall estimate.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Launch your career!

HK School of Management and Technology offers training in project management, job-search strategies, and career growth. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More