Network Logic

The complete set of dependency relationships that link activities within a project schedule network diagram.

Key Points

  • Represents all precedence ties among activities in the network diagram.
  • Includes relationship types (FS, SS, FF, SF) plus any leads and lags.
  • Drives sequencing, critical path, and total/free float calculations.
  • Covers mandatory, discretionary, and external dependencies and must be kept current as the schedule evolves.

Example

In a software release project: A: Define requirements -> B: Design (FS); B: Design -> C: Develop (FS with 2-day lead to start early); C: Develop -> D: Test (SS with 3-day lag); D: Test -> E: Deploy (FF). Together, these ties form the project's network logic.

PMP Example Question

Which term describes the full set of dependency relationships connecting activities in a project's schedule network diagram?

  1. Work Breakdown Structure
  2. Network Logic
  3. Resource Histogram
  4. Milestone List

Correct Answer: B — Network logic (the dependency ties among activities)

Explanation: Network logic is the collection of all activity dependencies in the schedule network diagram; the other options do not represent precedence relationships.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Become an AI-First Agile Leader!

HK School of Management and Technology helps you apply AI to Agile work with practical, prompt-based workflows for real-world Scrum challenges. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More