Monitoring and Controlling Process Group

The set of processes that watch and measure project work, compare results to the plan, control performance, determine where plan changes are needed, and carry out approved updates.

Key Points

  • Runs throughout the project to observe results and spot variances early.
  • Compares actual performance to scope, schedule, cost, and quality baselines using defined metrics.
  • Manages changes via integrated change control so only approved changes are implemented.
  • Produces corrective and preventive actions, updates to plans and documents, and performance reports.

Example

On a website redesign project, weekly metrics show pages delivered are behind the plan. The project manager reviews earned value data, identifies the schedule variance, submits a change request to re-sequence tasks and add a tester, gets approval through change control, updates the schedule baseline, and tracks whether the corrective action recovers the delay.

PMP Example Question

During execution, the team discovers a cost overrun and quality defects. Which action best represents the Monitoring and Controlling Process Group?

  1. Develop the project charter and business case.
  2. Direct and manage project work without updating baselines.
  3. Measure actual results against the plan, evaluate variances, and implement only approved changes.
  4. Obtain final acceptance and archive records.

Correct Answer: C — Measure performance and implement approved changes

Explanation: Monitoring and controlling focuses on comparing results to baselines, identifying needed changes, and applying those changes through formal change control.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Advance your Lean Six Sigma expertise!

HK School of Management and Technology helps you take Lean Six Sigma to the next level without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More