Monitor Risks

An ongoing process that oversees the execution of approved risk responses, keeps watch on known risks, discovers and assesses new risks, and checks how effective risk management is across the entire project.

Key Points

  • Continuous activity performed throughout the project life cycle.
  • Verifies that agreed risk responses are carried out and remain effective.
  • Updates the risk register and risk report with changes, new risks, and outcomes.
  • May trigger change requests, reserve adjustments, risk re-prioritization, or risk closing.

Example

On a software project, the team holds biweekly risk reviews. The project manager confirms the mitigation for a cybersecurity risk has been implemented, notes that defect trends are rising and adds a new risk about test environment instability, updates the risk register, and submits a change request to add a penetration test to strengthen the response.

PMP Example Question

Which process involves checking the effectiveness of risk responses, tracking known risks, and identifying new risks throughout the project?

  1. Plan Risk Management
  2. Perform Qualitative Risk Analysis
  3. Monitor Risks
  4. Control Quality

Correct Answer: C — Monitor Risks

Explanation: Monitor Risks is the ongoing process that oversees response execution, tracks existing risks, finds new risks, and evaluates risk management effectiveness during the project.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Stop Managing Admin. Start Leading the Future!

HK School of Management and Technology helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Enroll Now