Monitor and Control Project Work

An ongoing activity that measures, analyzes, and communicates overall project performance to ensure outcomes align with the objectives set in the project management plan.

Key Points

  • Continuously compares actual results with the plan to detect variances in scope, schedule, cost, and quality.
  • Converts work performance data into information and reports for decision-making and stakeholder communication.
  • Identifies issues and recommends corrective or preventive actions, often resulting in change requests.
  • Updates forecasts and project documents and provides inputs to integrated change control when changes are needed.

Example

The project manager reviews earned value metrics and status reports, finds the schedule is slipping, forecasts a later finish date, prepares a performance report for stakeholders, and submits a change request to add resources to recover the schedule.

PMP Example Question

Which process analyzes performance data, prepares work performance reports, and recommends actions to keep the project aligned with the plan?

  1. Direct and Manage Project Work
  2. Monitor and Control Project Work
  3. Perform Integrated Change Control
  4. Control Quality

Correct Answer: B — Monitor and Control Project Work

Explanation: This process tracks and analyzes overall performance, produces reports, and suggests corrective or preventive actions. Direct and Manage executes the work, Integrated Change Control approves changes, and Control Quality inspects deliverables.

AI Systems with Claude, for Scrum Masters and Project Managers

Most AI pilots in project management do not fail on the model. They fail because somebody pointed the thing at a decision instead of at a task. This course is built around that distinction, and around the work that follows once you get it right.

Eight teaching sections, taught against one running project from the first lecture to the last. You watch a system get built, then you build the same one against your own sprint. Nothing here is a demo that works only on the example.

You finish with five working systems and you keep them. The sprint report machine turns your board export and standup notes into the report you currently write by hand. The retro intelligence system tells you what the team keeps saying, not just what it said this time. The stakeholder comms engine drafts the update in the register the audience expects. The backlog health monitor flags the quiet decay nobody has time to check for. The risk and dependency tracker follows the chains that actually bite.

Seventy-six working files ship with it, across four sections, so every system is built against real sprint data rather than material invented for a slide. Four sprints of retrospectives, board exports, standup notes, backlog and risk data.

Explore the Course


Launch your career!

HK School of Management and Technology provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More