Lead

A time offset that allows a successor activity to begin (or finish) earlier than its predecessor would normally permit; it is the amount of time the successor is pulled forward relative to the predecessor.

Key Points

  • Often implemented as a negative lag in scheduling tools (e.g., FS - 2d), creating overlap between activities.
  • Can shorten the overall schedule by enabling parallel work, but may raise risk or rework if used excessively.
  • Should be logically justified and documented; do not use leads to mask schedule problems.
  • Applies to any dependency type (FS, SS, FF, SF), with FS plus lead being the most common case.

Example

Development and System Testing have a finish-to-start relationship. By applying a 2-day lead, Testing begins 2 days before Development is fully complete, allowing overlap and earlier feedback.

PMP Example Question

Activity B has a finish-to-start dependency on Activity A with a lead of 3 days. What does this indicate?

  1. B must start 3 days after A finishes.
  2. B can start 3 days before A finishes.
  3. B must finish 3 days before A starts.
  4. A can start 3 days earlier than planned.

Correct Answer: B — The successor starts 3 days earlier than the predecessor finishes.

Explanation: A lead advances the successor relative to the predecessor. With FS and a 3-day lead, B begins 3 days before A's finish.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More