Late Start Date (LS)

In critical path method scheduling, the latest time an activity can begin its remaining work without delaying the project, as dictated by the network logic, the required project finish date, and any schedule constraints.

Key Points

  • Calculated during the backward pass of the critical path method.
  • Driven by successor relationships, the target project completion date, and schedule constraints; tighter limits reduce the LS.
  • Computed as LS = LF - duration, accounting for any leads or lags.
  • On the critical path (zero total float), LS equals ES.

Example

Assume the project must finish by day 60. Activity X has a duration of 6 days, and the backward pass yields a latest finish (LF) of day 40. The late start (LS) is 40 - 6 = day 34. Starting Activity X after day 34 would push its finish beyond day 40 and risk delaying the overall project.

PMP Example Question

An activity has a duration of 4 days and a latest finish (LF) of day 18. What is its late start (LS)?

  1. Day 14
  2. Day 18
  3. Day 22
  4. Cannot be determined without early dates

Correct Answer: A — Late start is day 14

Explanation: LS = LF - duration = 18 - 4 = 14. Early dates are not needed to compute LS from LF and duration.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.



Launch your career!

HK School of Management provides world-class training in Project Management with AI and Agile Methodologies. Just for the price of a lunch you can transform your career, and reach new heights. With 30 days money-back guarantee, there is no risk.

Learn More