Late Finish Date (LF)

In critical path method (CPM), the Late Finish Date is the latest time an activity's remaining work can be completed without moving the project completion date, as determined by the schedule network logic and any schedule constraints.

Key Points

  • Calculated during the backward pass of CPM analysis.
  • Driven by network logic, the required project finish date, and any constraints or deadlines.
  • For activities on the critical path, LF equals EF (total float is zero).
  • Total float can be computed as LF - EF (equivalently LS - ES).

Example

A project must complete by day 60. The backward pass shows Activity D has LF = day 40. If Activity D finishes after day 40, the project would slip past day 60, so day 40 is its latest allowable finish without delaying the overall completion.

PMP Example Question

While performing a backward pass, the team wants to find the latest date Activity X can finish without delaying the project finish. Which value are they determining?

  1. Early Finish Date (EF)
  2. Late Start Date (LS)
  3. Late Finish Date (LF)
  4. Free Float

Correct Answer: C — Late Finish Date

Explanation: LF is the latest permissible finish for an activity based on the schedule network, project completion date, and any constraints, identified during the backward pass.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.



Stop Managing Admin. Start Leading the Future!

HK School of Management helps you master AI-Prompt Engineering to automate chaos and drive strategic value. Move beyond status reports and risk logs by turning AI into your most capable assistant. Learn the core elements of prompt engineering to save hours every week and focus on high-value leadership. For the price of lunch, you get practical frameworks to future-proof your career and solve the blank page problem immediately. Backed by a 30-day money-back guarantee-zero risk, real impact.

Enroll Now