Issue

A present condition or circumstance that could influence or affect the project's objectives.

Key Points

  • Exists now and requires attention; unlike a risk, it is not uncertain.
  • Recorded in an issue log with an owner, priority, and target resolution date.
  • May need escalation or decisions and can trigger change control if baselines are impacted.
  • Can affect scope, schedule, cost, quality, resources, or stakeholder satisfaction.

Example

During system testing, a critical interface fails, blocking progress. The project manager logs an issue, assigns an owner to investigate, assesses impacts on the test schedule and budget, escalates to the sponsor for a decision, and raises a change request if the plan must be adjusted.

PMP Example Question

A stakeholder reports that last night's data migration failed and testing cannot proceed. How should the project manager categorize and handle this?

  1. Add it as a risk and plan a response later.
  2. Log it as an issue, assign an owner, manage it through the issue process, and initiate change control if needed.
  3. Treat it as an assumption to be validated.
  4. Document it as a dependency and continue with the plan.

Correct Answer: B — Log and manage it as an issue

Explanation: The event has already occurred and is affecting objectives now, so it is an issue requiring immediate tracking, ownership, and potential change control.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More