Free Float

The maximum time an activity can slip without pushing the early start of any successor or breaking a schedule constraint.

Key Points

  • Free float is measured for a single activity relative to its immediate successors.
  • Computed as the earliest successor's early start minus the activity's early finish, adjusted for leads/lags and constraints.
  • If a successor is scheduled to start as soon as this activity finishes, the free float is zero.
  • Different from total float, which is based on the overall path or project finish date.

Example

Activity B finishes (EF) on day 8. Its earliest successor, Activity C, has an early start (ES) on day 10. Free float for Activity B is 2 days (10 - 8). B can be delayed up to 2 days without delaying C's early start or violating any schedule constraint.

PMP Example Question

Which statement best describes free float?

  1. The total time an activity can slip without delaying the project completion date.
  2. The time an activity can be delayed without delaying the early start of any successor or violating a schedule constraint.
  3. The slack available to the entire network path on which the activity lies.
  4. The extra time created by assigning additional resources to an activity.

Correct Answer: B — The time an activity can be delayed without pushing a successor's early start or breaking a constraint

Explanation: Free float looks only at the relationship between an activity and its successors, not the overall project finish or full path slack.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.

Explore the Course


Become an AI-First Agile Leader!

HK School of Management and Technology helps you apply AI to Agile work with practical, prompt-based workflows for real-world Scrum challenges. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More