Forward Pass

A Critical Path Method step that calculates each activity's early start and early finish by moving forward through the schedule network from the project start date or another defined starting point.

Key Points

  • Moves left-to-right through the network, accumulating durations along logical links.
  • Determines the earliest possible dates; used with the backward pass to find float and late dates.
  • Needs activity durations, dependencies, and a specified start or data date.
  • Does not account for resource limits unless resource leveling is applied afterward.

Example

On a project starting June 1, Activity A (3 days) precedes Activity B (2 days) and Activity C (4 days). Running the forward pass: A ES/EF = Jun 1/Jun 3, B ES/EF = Jun 4/Jun 5, C ES/EF = Jun 4/Jun 7. The project’s earliest completion is Jun 7, pending downstream activities and paths.

PMP Example Question

Which scheduling technique computes early start and early finish dates by progressing from the project start through the network?

  1. Forward pass
  2. Backward pass
  3. Resource leveling
  4. What-if analysis

Correct Answer: A — Forward pass

Explanation: The forward pass calculates the earliest dates by moving forward through the schedule. The backward pass calculates late dates, while the other options serve different purposes.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.



Build complete project plans in minutes with AI

Stop spending hours on documentation. Learn how to use AI to create charters, WBS, schedules, risk registers, and executive reports faster—while staying fully in control. This course gives you ready-to-use prompt templates and practical workflows based on real project work. No guesswork, no fluff—just tools you can apply immediately. Backed by Udemy’s 30-day money-back guarantee, so you can start risk-free.

Learn More