Forward Pass

A Critical Path Method step that calculates each activity's early start and early finish by moving forward through the schedule network from the project start date or another defined starting point.

Key Points

  • Moves left-to-right through the network, accumulating durations along logical links.
  • Determines the earliest possible dates; used with the backward pass to find float and late dates.
  • Needs activity durations, dependencies, and a specified start or data date.
  • Does not account for resource limits unless resource leveling is applied afterward.

Example

On a project starting June 1, Activity A (3 days) precedes Activity B (2 days) and Activity C (4 days). Running the forward pass: A ES/EF = Jun 1/Jun 3, B ES/EF = Jun 4/Jun 5, C ES/EF = Jun 4/Jun 7. The project’s earliest completion is Jun 7, pending downstream activities and paths.

PMP Example Question

Which scheduling technique computes early start and early finish dates by progressing from the project start through the network?

  1. Forward pass
  2. Backward pass
  3. Resource leveling
  4. What-if analysis

Correct Answer: A — Forward pass

Explanation: The forward pass calculates the earliest dates by moving forward through the schedule. The backward pass calculates late dates, while the other options serve different purposes.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Stop Managing Admin. Start Leading the Future!

HK School of Management and Technology helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Enroll Now