Flowchart

A diagram that visually maps one or more processes by showing their inputs, steps (including decisions), and resulting outputs within a system.

Key Points

  • Shows the sequence of activities and decision points in a process.
  • Uses standard symbols (start/end, process, decision, connectors) to improve clarity.
  • Helps uncover bottlenecks, rework loops, and handoff issues.
  • Useful for process mapping, quality management, and stakeholder communication.

Example

A project team documents its change control process with a flowchart: inputs include a submitted change request; steps cover initial screening, impact analysis, change control board decision, and implementation; outputs include an approved/Rejected change and updated baselines and logs.

PMP Example Question

During a process improvement effort, the team wants a visual that traces inputs through steps and decision points to the resulting outputs across a process. Which tool should the project manager use?

  1. Flowchart
  2. Pareto chart
  3. Responsibility assignment matrix
  4. Control chart

Correct Answer: A — Flowchart

Explanation: A flowchart depicts inputs, activities, decisions, and outputs of one or more processes. The other options analyze data or roles, not the step-by-step flow.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More