Float

The amount of schedule flexibility for an activity or path, expressed as how long it can be delayed without creating a defined impact. In practice, this flexibility is measured as total float when the impact is the project finish date, or as free float when the impact is the start of the immediate successor.

Key Points

  • Also called slack. See total float and free float.
  • Calculated via critical path method by comparing early and late dates from forward and backward passes.
  • Activities on the critical path typically have zero total float; negative float indicates a schedule that violates an imposed date.
  • Float is consumable and can be reduced by changes, risk responses, or resource leveling, so it should be monitored and managed.

Example

In a sequence A -> B -> C, B is planned to finish on day 6 and C is scheduled to start on day 9. B can slip to finish as late as day 9 without delaying C, so B has 3 days of free float. If the project finish depends on C, B also has 3 days of total float.

PMP Example Question

Which statement best describes float in a project schedule?

  1. The budget reserve available to absorb cost overruns.
  2. The time an activity can slip before affecting a defined schedule date, such as the project finish or a successor's start.
  3. The difference between optimistic and pessimistic duration estimates.
  4. Idle time caused by resource underutilization.

Correct Answer: B — time an activity can slip before affecting a specified schedule date

Explanation: Float represents schedule flexibility; common forms are total float (relative to project finish) and free float (relative to the successor's start).

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Become an AI-First Agile Leader!

HK School of Management empowers you to master AI as your most powerful co-pilot—without the complexity. Transform your agile leadership with practical, prompt-based workflows and proven strategies designed for real-world scrum challenges. For the price of lunch, you get the tools to automate mundane tasks, refine backlogs with precision, and drive unprecedented efficiency in your team. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More