Fixed-Price Contract

A contract where a single, fixed price is agreed for a clearly defined scope of work, and payment stays the same regardless of the actual costs or effort required to deliver it.

Key Points

  • Price is set upfront and does not change with the seller's actual costs or effort.
  • Best suited when scope, specifications, and deliverables are stable and well-defined.
  • Cost overrun risk is largely on the seller; the buyer gains predictable total cost.
  • Scope changes require formal change control and may lead to a negotiated price adjustment.

Example

A company hires a vendor to build a website for a fixed price of $120,000 based on a detailed requirements document. Even if the vendor spends more time or money than planned, the buyer still pays $120,000 unless an approved change request modifies the scope and price.

PMP Example Question

Which contract type provides the buyer with the greatest cost certainty while placing most cost risk on the seller for a well-defined scope?

  1. Time and Materials (T&M)
  2. Fixed-Price
  3. Cost-Plus-Fixed-Fee (CPFF)
  4. Cost-Plus-Incentive-Fee (CPIF)

Correct Answer: B — Fixed-Price Contract

Explanation: In a fixed-price contract, the total price is set for a defined scope, giving the buyer cost predictability while the seller bears the risk of cost overruns.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Advance your Lean Six Sigma expertise!

HK School of Management and Technology helps you take Lean Six Sigma to the next level without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More