Finish Date

The specific point in time when a scheduled activity is completed, typically labeled as actual, planned, estimated, scheduled, early, late, baseline, target, or current.

Key Points

  • Identifies when an activity is considered complete in the schedule model.
  • Can be qualified (e.g., actual, planned, estimated, scheduled, early, late, baseline, target, current).
  • Differs from start date and from the activity's duration; it marks completion, not effort.
  • Used for tracking performance, forecasting, and comparing against the baseline in Gantt/CPM schedules.

Example

Activity "Install Servers" has a baseline finish date of May 10. After analysis, the scheduled early finish is May 8. The team completes the work on May 9, which becomes the actual finish date. These qualifiers help compare plan versus performance.

PMP Example Question

In a project schedule, what does the term "finish date" most accurately represent?

  1. The total time required to complete an activity
  2. The specific time associated with an activity's completion, which may be actual, planned, estimated, scheduled, early, late, baseline, target, or current
  3. The date a key resource becomes available to the project
  4. The formal deadline for issuing the project charter

Correct Answer: B — The time point marking activity completion with a qualifier

Explanation: The finish date marks when an activity completes and is often indicated with qualifiers (e.g., actual, baseline), distinguishing it from duration or unrelated project milestones.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Advance your Lean Six Sigma expertise!

HK School of Management and Technology helps you take Lean Six Sigma to the next level without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More