Estimate to Complete (ETC)

The forecasted amount of money needed to complete all unfinished work on the project.

Key Points

  • ETC represents only the future cost from today to project completion, not what has already been spent.
  • It links to total forecast: EAC = AC + ETC, so ETC = EAC - AC.
  • You can compute ETC by a bottom-up reestimate of remaining work or by deriving it from an EAC formula based on performance assumptions.
  • Official PMI wording: "The expected cost to finish all the remaining project work."

Example

A project has BAC = $500,000, EV = $250,000, and AC = $300,000. Assuming future cost performance will mirror past performance (use CPI), first find EAC: EAC = AC + (BAC - EV) / CPI. With CPI = EV / AC = 250,000 / 300,000 = 0.833, EAC ≈ 300,000 + 250,000 / 0.833 ≈ 300,000 + 300,000 = $600,000. Therefore, ETC = EAC - AC = 600,000 - 300,000 = $300,000.

PMP Example Question

A project reports AC = $1.2M, EV = $1.0M, and BAC = $2.0M. The PM expects future work to continue at the current CPI. What is the Estimate to Complete (ETC)?

  1. $0.8M
  2. $1.0M
  3. $1.2M
  4. $2.0M

Correct Answer: C — $1.2M

Explanation: CPI = EV/AC = 1.0/1.2 = 0.833. EAC = AC + (BAC - EV)/CPI = 1.2 + (1.0)/0.833 ≈ 2.4 (in millions). ETC = EAC - AC = 2.4 - 1.2 = 1.2M.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More