Estimate Activity Resources

The planning process used to figure out what people are needed and to quantify the types and amounts of materials, equipment, and supplies required to complete the project activities.

Key Points

  • Determines labor needs (skills, roles, quantities) for each activity.
  • Calculates the kinds and amounts of materials, equipment, and consumables required.
  • Produces resource requirements and the basis of estimates; may create a resource breakdown structure.
  • Informs scheduling and cost estimating and is refined as plans and risks evolve.

Example

On a website launch project, the team estimates that the "Build API" activity needs 2 backend developers for 3 weeks, 1 QA tester for 1 week, a staging server for 2 weeks, and test data sets. For "UX Validation," they estimate 1 UX researcher for 1 week, 10 participant incentives, and 5 tablets for usability testing.

PMP Example Question

Which process determines the number and types of team members and the quantities of materials and equipment needed for each activity?

  1. Develop Team
  2. Estimate Costs
  3. Estimate Activity Resources
  4. Acquire Resources

Correct Answer: C — Estimate Activity Resources

Explanation: Estimate Activity Resources identifies the people, materials, equipment, and supplies needed for activities. Acquire Resources obtains those resources; Estimate Costs focuses on monetary values; Develop Team improves team competencies.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Stop Managing Admin. Start Leading the Future!

HK School of Management helps you master AI-Prompt Engineering to automate chaos and drive strategic value. Move beyond status reports and risk logs by turning AI into your most capable assistant. Learn the core elements of prompt engineering to save hours every week and focus on high-value leadership. For the price of lunch, you get practical frameworks to future-proof your career and solve the blank page problem immediately. Backed by a 30-day money-back guarantee-zero risk, real impact.

Enroll Now