Earned Value (EV)

The budgeted value of the work actually completed to date, found by applying the authorized budget for that scope to the percent complete.

Key Points

  • EV represents how much value has been earned in budget terms for the work finished by the status date.
  • Basic formula: EV = Percent Complete × Budget for that scope (e.g., a work package budget or BAC for the whole project).
  • Used with AC (Actual Cost) and PV (Planned Value) to compute CV, SV, CPI, and SPI.
  • EV reflects progress against the baseline; it is not the money spent (AC) nor the amount planned by now (PV).

Example

A project has a BAC of USD 500,000. By the status date, the team has completed 40% of the total scope. EV = 0.40 × 500,000 = USD 200,000. If AC = USD 230,000 and PV = USD 250,000, then CV = EV − AC = −USD 30,000 (over budget) and SV = EV − PV = −USD 50,000 (behind schedule).

PMP Example Question

A work package has an authorized budget of USD 80,000 and is 35% complete at the status date. What is the Earned Value (EV)?

  1. USD 28,000
  2. USD 35,000
  3. USD 80,000
  4. USD 45,000

Correct Answer: A — EV is USD 28,000

Explanation: EV = Percent Complete × Budget = 0.35 × 80,000 = 28,000.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Stop Managing Admin. Start Leading the Future!

HK School of Management and Technology helps you learn AI prompt engineering for project work. Move beyond status reports and risk logs with practical prompt frameworks for everyday tasks. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Enroll Now