Early Start Date (ES)

In CPM scheduling, ES is the first moment the remaining portion of an activity is allowed to begin, determined by the schedule network relationships, the current data (status) date, and any imposed schedule constraints.

Key Points

  • Calculated during the forward pass of the critical path method.
  • Driven by network logic, the data/status date, and schedule constraints (e.g., SNET).
  • Determines Early Finish: EF = ES + activity duration.
  • On the critical path, ES equals LS because total float is zero.

Example

Activity B (3 days) has a finish-to-start relationship with Activity A. A completes at the end of day 5. The data date is day 5 and there are no constraints. The ES for B is day 6, so its EF is day 8.

PMP Example Question

Which statement best defines the Early Start Date (ES) of a schedule activity in CPM?

  1. The earliest time the remaining work can start, based on network logic, the data date, and any constraints.
  2. The latest time the activity can start without delaying the project finish.
  3. The actual start recorded for the activity.
  4. The planned start from the approved baseline.

Correct Answer: A — The earliest allowed start based on logic, status date, and constraints

Explanation: ES is computed in the forward pass using the schedule network logic, the current data/status date, and any schedule constraints to find the earliest feasible start.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More