Determine Budget

The process of summing the cost estimates for activities or work packages to create the approved project cost baseline.

Key Points

  • Totals activity and work package estimates to form a time-phased cost baseline.
  • Includes contingency reserves in the baseline; management reserves sit outside the baseline but count toward the total project budget.
  • Uses inputs such as cost estimates, scope and schedule baselines, resource rates, risk data, and historical information; techniques include cost aggregation, reserve analysis, and funding limit reconciliation.
  • Primary outputs are the cost baseline and project funding requirements, plus updates to relevant documents.

Example

A construction PM rolls up the estimated costs of foundation, framing, electrical, and plumbing work packages, adds contingency for identified risks, aligns the spending plan with quarterly funding limits, and produces the approved cost baseline used to track performance.

PMP Example Question

A PM is consolidating work package cost estimates to produce the time-phased budget used for cost performance measurement. Which process is being performed?

  1. Estimate Costs
  2. Determine Budget
  3. Control Costs
  4. Plan Cost Management

Correct Answer: B - Determine Budget

Explanation: Determine Budget aggregates cost estimates into an approved cost baseline used to measure and control cost performance.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included