Critical Path Method (CPM)

A scheduling technique that calculates the shortest possible project duration and measures the amount of float on each logical path in the schedule network.

Key Points

  • Identifies the critical path: the longest path through the network with zero total float; any delay on it delays the project finish.
  • Uses forward and backward pass to compute early/late start and finish dates and total float for activities and paths.
  • The critical path can shift during execution, and there can be multiple critical paths in some schedules.
  • Informs schedule compression choices (crashing, fast tracking) and highlights where schedule flexibility exists.

Example

A project schedule lists activities with durations and dependencies. The team draws the network diagram and runs forward and backward passes to find early/late dates. The path A-B-D-E totals 40 days with zero float, while path A-C-E totals 35 days with 5 days of float. To finish sooner, the manager considers crashing activities on A-B-D-E since only shortening the critical path reduces the overall project duration.

PMP Example Question

Which technique determines the minimum project duration and identifies where schedule float exists across network paths?

  1. Critical Path Method (CPM)
  2. Program Evaluation and Review Technique (PERT)
  3. Monte Carlo simulation
  4. Resource leveling

Correct Answer: A — Critical Path Method (CPM)

Explanation: CPM calculates early and late dates, total float, and the longest path, revealing the minimum project duration and schedule flexibility.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Ready to lead the future of agile and make data-driven decisions that cut through complexity? Join a community of forward-thinking professionals and position yourself as an indispensable leader in the AI era. Enroll now and unlock your future!



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More