Create WBS

The act of breaking project deliverables and the work required into smaller, controllable pieces so they can be estimated, scheduled, and managed.

Key Points

  • Produces a hierarchical Work Breakdown Structure focused on deliverables; the lowest level is a work package.
  • Uses decomposition and stops when work packages are clear enough to plan, estimate, and control.
  • Applies the 100% rule to capture the entire scope with no gaps or overlap.
  • Key outputs include the WBS, WBS dictionary, and updates to the scope baseline and related documents.

Example

A project to develop a mobile app is decomposed into deliverables such as Requirements, Design, Development, Testing, and Release. Each deliverable is further split (e.g., Development into Front-end, Back-end, and Integration), and then into work packages like "Implement login API" or "Build onboarding UI" that can be estimated and assigned.

PMP Example Question

Which activity best represents the Create WBS process?

  1. Breaking deliverables into hierarchical work packages to form the scope baseline.
  2. Sequencing activities to build the project schedule network diagram.
  3. Identifying stakeholders and documenting their expectations.
  4. Estimating durations for each defined activity.

Correct Answer: A — Decomposing deliverables into work packages

Explanation: Create WBS focuses on deliverable-oriented decomposition to produce the WBS and related components of the scope baseline, not on sequencing, stakeholder identification, or duration estimating.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More