Cost Plus Fixed Fee Contract (CPFF)

A cost-reimbursable agreement where the buyer pays the seller's allowable, contract-defined costs and adds a predetermined fixed fee as profit.

Key Points

  • Buyer reimburses allowable costs; profit is a fixed fee agreed at contract award.
  • The fixed fee does not vary with actual cost performance; it changes only through approved contract modifications.
  • Most cost risk rests with the buyer; the seller is protected on profit but must manage costs responsibly.
  • Best used when scope or effort is uncertain (e.g., R&D), and strong cost tracking and audits are required.

Example

A government agency hires a vendor to develop a novel prototype under CPFF. The contract allows reimbursement of all allowable labor, materials, and testing costs, plus a fixed fee of $300,000. If allowable costs end up at $4.2M, the total paid is $4.5M; if costs are $3.8M, the total is $4.1M. In both cases, the fee remains $300,000.

PMP Example Question

Which contract type pays the seller for allowable costs and provides a profit that remains constant regardless of actual costs?

  1. Cost Plus Fixed Fee (CPFF)
  2. Cost Plus Incentive Fee (CPIF)
  3. Firm Fixed Price (FFP)
  4. Time and Materials (T&M)

Correct Answer: A — Cost Plus Fixed Fee (CPFF)

Explanation: In CPFF, the buyer reimburses allowable costs and pays a fixed profit fee that does not change with actual cost outcomes.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.

Explore the Course


Become an AI-First Agile Leader!

HK School of Management and Technology helps you apply AI to Agile work with practical, prompt-based workflows for real-world Scrum challenges. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More