Cost Baseline

The formally approved, time-phased budget for the project that excludes management reserves; it can only be modified through the formal change control process and serves as the benchmark for comparing actual cost performance.

Key Points

  • Represents the authorized, time-phased plan for project spending.
  • Excludes management reserves but includes contingency reserves.
  • Changes are allowed only via formal change control.
  • Used as the cost benchmark for tracking and Earned Value analysis.

Example

A $1.2M cost baseline is spread across 12 months. Midway through the project, actual costs run $30K over the plan in month 6. The team compares the variance to the baseline and requests a formally approved change to rephase funds due to supplier delays.

PMP Example Question

Which artifact is the time-phased plan for spending that excludes management reserves and is used to compare actual costs during execution?

  1. Cost Management Plan
  2. Project Budget
  3. Cost Baseline
  4. Performance Measurement Baseline

Correct Answer: C — Cost Baseline

Explanation: The cost baseline is the approved, time-phased budget excluding management reserves and is the reference for measuring actual cost performance.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More