Corrective Action

A deliberate step taken to bring actual project results back into alignment with the approved project management plan.

Key Points

  • Used after a variance is detected to restore performance to planned targets.
  • May require an approved change request if it affects baselines or constraints.
  • Different from preventive action (avoids future variances) and defect repair (fixes product defects).
  • Guided by monitoring and controlling data such as EVM, trend analyses, and control charts.

Example

The project is behind schedule with an SPI of 0.85. The project manager requests to fast-track selected activities and add one tester to recover the schedule and match the schedule baseline. This is a corrective action.

PMP Example Question

During execution, the team identifies a cost overrun and submits a change request to re-sequence work and negotiate a discount with a vendor to realign with the cost baseline. What is this an example of?

  1. Preventive action
  2. Workaround
  3. Corrective action
  4. Defect repair

Correct Answer: C — Corrective action

Explanation: The action addresses an existing variance to bring performance back in line with the plan. Preventive action avoids potential issues, a workaround is an unplanned response to a realized risk, and defect repair fixes product defects.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Lead with clarity, influence, and outcomes.

HK School of Management and Technology offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More