Control Schedule

A continuous activity that tracks project progress, updates the schedule to reflect actual performance, and governs approved changes to the schedule baseline.

Key Points

  • Compares actual progress against the schedule baseline to identify variances.
  • Updates the schedule model and forecasts completion dates using current performance data (e.g., SV, SPI).
  • Submits and manages change requests to the schedule baseline through integrated change control.
  • May apply techniques such as critical path analysis, what-if analysis, and schedule compression (crashing/fast tracking).

Example

Midway through a software project, several critical-path tasks slip. The project manager records actual start/finish dates, recalculates the critical path, forecasts a two-week delay, and evaluates fast tracking to recover time. Because the change affects the baseline finish date, the PM raises a change request for approval and then updates the baseline and schedule once approved.

PMP Example Question

During execution, the team reports multiple delays on critical activities. What is the most appropriate next step in Control Schedule?

  1. Rebaseline the schedule immediately to reflect the new dates.
  2. Analyze impacts, update actuals, forecast outcomes, and submit a change request for any baseline changes.
  3. Ask the sponsor to extend the project deadline informally.
  4. Add more resources to all late activities without reviewing the critical path.

Correct Answer: B — Analyze, update, forecast, and manage changes through the change control process

Explanation: Control Schedule requires measuring performance, updating the schedule, forecasting, and processing any needed baseline changes via integrated change control, not rebaselining or making unilateral changes.

How To Land the Job and Interview for Project Managers Course

Take the next big step in your project management career with HK School of Management and Technology. Whether you're breaking into the field or aiming for your dream job, this course gives you the tools to stand out, impress in interviews, and secure the role you deserve.

This isn’t just another job-hunting guide—it’s a tailored roadmap for project managers. You’ll craft winning resumes, tackle tough interview questions, and plan your first 90 days with confidence. Our hands-on approach includes real-world examples, AI-powered resume hacks, and interactive exercises to sharpen your skills.

You'll navigate the hiring process like a pro, with expert insights on personal branding, salary negotiation, and career growth strategies. Plus, downloadable templates and step-by-step guidance ensure you're always prepared.

Learn from seasoned professionals and join a community of ambitious project managers. Ready to land your ideal job and thrive in your career? Enroll now and take control of your future!

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course